New Accessory Dwelling Unit (ADU) in Redland California was just completed January 2024! This 2-bed, 2-bath detached unit, spanning 749 sq ft, is now a beautiful rental property.

Project Overview

  • Location: Southern California
  • Size: 2 bedrooms, 2 bathrooms, 749 sq ft, detached
  • Total Cost: Approximately $287K

Property Details

This ADU is situated on a corner lot with a large side yard (80′ deep by 40′ wide), making it an ideal setup for an additional dwelling. Here’s a breakdown of the project timeline and costs:

  • April 2022: Hired a designer (despite facing many challenges with the company, we had a clear vision for our design)
  • November 2022: Submitted plans
  • January 2023: Plans approved
  • April 2023: Hired a general contractor and started building
  • Mid-December 2023: Construction completed
  • Early January 2024: Passed final inspection
  • Mid-January 2024: Rented out immediately

Costs Breakdown

  • Design: $9K
  • City & School Permits: $10K
  • Build Cost: $205K
  • Finishes: $18K
  • Appliances: $6K
  • Fence: $5K
  • Landscaping: $12K (partially for the main house)
  • Hardscape: $5K
  • Pool Removal: $17K